The July 15, 2025 NYSDOT Main Street Bridge Update:
This week, Crane Hogan will continue to finish Punch List work and subcontractors finalize their efforts: BVR Ironworkers will re-install the guide rail, Champion is working on the operating console, and O’Connell continues electrical work. Electrical testing continues next week, with any modifications to be wrapped up Wednesday/Thursday and the operating console work will be finished Thursday-Saturday. Functional testing will begin July 28, including nighttime testing, with the bridge in the lower position. Testing will include warning gates and barrier lights. Temporary warning lights for mariners will be installed.
The bridge is scheduled to open mid-week the week of August 4th.