by Carol McNees | Mar 24, 2025 | Announcements, Bridging the Closure, News
Multiple crews are on site (O’connell—electric, BVR—steel, Crane Hogan—contractor) and are working on the weekends. Concrete covers for the pits will be completed in the next couple of weeks as soon as all machinery for the pits is in place. All machinery is on...
by Carol McNees | Mar 12, 2025 | Announcements, Bridging the Closure, News
Here’s the latest from NYSDOT. All the remaining pieces and parts for the bridge are on site and in the process of being assembled. Now that the lifting posts, whose delayed delivery held up work for several months, are in place and operational, the bridge can be...
by Carol McNees | Jan 29, 2025 | Announcements, Bridging the Closure, News
Here are the major tasks that need to be completed on the Main Street bridge before it can open. Millwrights and steel workers— all attention now focused on the Brockport bridge since the Albion bridge has opened to traffic, Lifting posts south side in place,...
by Carol McNees | Jan 21, 2025 | Announcements, Bridging the Closure, News
By Mayor Blackman A long overdue update on the Main Street bridge which is behind schedule. I met with the engineer in charge from the DOT to review what the scheduling issues are and what remains to be done. There is a “critical path of assembly” of bridge...
by Carol McNees | Nov 12, 2024 | Announcements, Bridging the Closure, News
The mayor recently spoke with Paul Attoma, Engineer in Charge to get an update on the Main Street bridge work. They have milled the approaches to the north and south sides of the bridge and will be paving them this week. Steel plates will be put over the approaches...
by Carol McNees | Sep 18, 2024 | Announcements, Bridging the Closure, News, Uncategorized
Counterweight sheaves, painted safety orange, to be installed in the north pit on Friday September 20th. Each weighs 25,000 lbs.